PREFABRICATING 8 MILES OF PIPE RACKS TO MEET THE RENOVATION SCHEDULE.

PROJECT NAME.

Sidney Yates Building Renovation

CUSTOMER.

Grunley Construction

MARKET SECTOR.

Government

SERVICES.

Design-Assist

Engineering Peer Review

Virtual Design & Construction (BIM Modeling)

Prefabrication

Mechanical Construction

THE CHALLENGE.

The Sidney Yates Building, originally built between 1878-80, is a 180,000 square foot facility on the national historic registry. The facility includes historic rooms, entries, staircases, and other features. Limbach was involved before there were any design documents. Limbach’s contract was based on narrative and as-builts only.

  • Tight schedule
  • Incomplete design documents at the time of equipment release

THE SOLUTION.

Limbach developed a fast-track solution that would effectively implement the Owner’s required system. The central Air Handling Units, return fans, and VAV boxes were replaced, and new chilled water and hot water pumps were selected to serve the new 4-pipe system.

All equipment was submitted and released to fabrication with the preliminary 35% design submission to GSA. Additionally, the new 4 pipe distribution had to fit within very tight perimeter enclosures. Limbach worked with RTKL to develop a 4-pipe tracking solution that would allow extensive sections of piping to be fabricated while demolition occurred, and also fit within a very tight enclosure.

The resulting prefabricated rack system allowed 8 miles of piping to be installed in less than 3 months during the middle of the project.

*This project was awarded the DBIA-MAR Renovation, Design-Build Award (2014)

*This project was also LEED-Silver Certified.